Pole Attachment Programs Don't Break Down in the Field. They Break Down Between Systems.

By Mia Diya-Bernhard, P.E., PMP | President & CEO, Aeparmia Engineering

Over my career working with Texas utilities, I have seen joint-use teams do remarkable work with limited staff and even more limited time. Their engineering is usually sound. What wears them down is everything around the engineering: the handoffs between departments, the systems that don’t talk to each other, the paperwork, and the compliance obligations that sit between an attachment application and a finished, correctly billed attachment.

Fiber buildouts, broadband funding and small cell deployments are now sending applications to utilities faster than most attachment programs were built to handle. More engineering alone won’t close that gap. What’s needed is program management, and that is where we focus.

Where the Pain Shows Up

Every program is different, but when we audit attachment programs, the same pain points come up again and again:

  • The same pole gets fielded more than once. The applicant collects data, then the utility collects it again, then a post-construction inspection starts from scratch because the earlier data didn’t carry forward. Each trip costs time and money.
  • Make-ready is hard to document and harder to defend. Photos, loading results, field notes and approvals end up in email threads, shared drives and spreadsheets. When a dispute or audit comes, rebuilding the record takes days.
  • Staff enter the same data into several systems. One application may be typed into a mapping system, a notification system, a work order system and a billing system, each by hand. Every manual entry is a chance for error.
  • Billing falls behind the work. Application fees, make-ready charges, inspection costs and annual rental depend on accurate attachment counts. When records don’t match, revenue goes uncollected and disputes get harder to settle.
  • Standards are outdated or scattered. When specifications, construction details and procedures are unclear, each applicant reads them differently, and reviews become inconsistent.
  • Compliance lives in people’s heads. Agreement terms, NESC clearances, safety requirements and regulatory reporting are often tracked informally. When a key person leaves, that knowledge leaves with them.

The Rules Depend on Who Owns the Pole

Pole attachment obligations in Texas depend on who owns the pole. Most of the utilities we work with are municipally owned, and their rules are different from those that govern investor-owned utilities and electric cooperatives. Knowing which rules apply is the first step in building a program that meets them.

Pole ownerWhat governs attachments
Municipally owned utilities

Not regulated by the FCC under 47 U.S.C. §224.

Texas Utilities Code §54.204 bars discrimination against certificated telecommunications providers in attachment rates and terms, requires a single, uniform rate for non-affiliated attachers, and caps that rate at what the FCC formula would allow. The PUCT enforces it.

Local Government Code §284.201 requires municipally owned utilities to allow small cell collocation on nondiscriminatory terms under a negotiated pole attachment agreement. Timelines come from your own attachment agreement.

Electric cooperatives

Not regulated by the FCC under 47 U.S.C. §224.

Texas Utilities Code Chapter 253 governs broadband attachments to cooperative distribution poles, including applications, contracts, rates and cost-based charges.

Investor-owned electric utilitiesFCC pole attachment rules apply, including the access timelines in 47 CFR §1.1411.

For a municipally owned utility, this means the attachment agreement does much of the work that federal rules do for an investor-owned utility. If your agreement doesn’t set clear application, survey, make-ready and payment timelines, your program has nothing firm to manage to, and nothing to point to when an attacher disputes a delay or a charge. And because state law requires a single, uniform rate, inconsistent attachment records and billing are harder to defend.

The Clock Is Already Running

Federal timelines shape expectations even where they don’t apply. The FCC’s pole attachment timelines apply to investor-owned utilities under 47 U.S.C. §224. They do not apply to municipally owned utilities or electric cooperatives, which are excluded from the federal definition of a utility. Attachers who build across Texas know these timelines from their work with investor-owned utilities, and they often expect the same pace on municipal and cooperative poles.

FCC Pole Attachment Timelines

Pole access phaseRegular ordersMid-sized ordersLarge orders
Application completeness review10 business days10 business days10 business days
Survey and review on the merits45 days60 days90 days
Make-ready estimate14 days after survey14 days after survey29 days after survey
Communications space make-ready30 days after notice75 days after notice120 days after payment
Above communications space make-ready90 days after notice135 days after notice180 days after payment

Source: 47 CFR §1.1411 and FCC 25-38. Make-ready periods for regular and mid-sized orders run from the utility’s notice to existing attachers, issued after the attacher’s payment. These timelines apply to utilities subject to Section 224 and do not apply to municipally owned utilities or electric cooperatives.

For municipally owned utilities and electric cooperatives, these timelines are not mandatory, but attachers working across multiple utility systems will know them. That makes it even more important for a municipal or cooperative attachment agreement to set its own application review, survey, make-ready, construction and payment timelines rather than leaving those expectations undefined.

In 2025, the FCC also added advance notice requirements for mid-sized and large orders, a meet and confer requirement for large orders, and a self-help process that lets attachers prepare their own make-ready estimates when a utility misses its deadline, subject to specific limits. The new large order timelines and related changes took effect May 7, 2026.

Pole Inspection Requirements Apply to All Three

Separate from pole attachment rules, HB 144 (Texas Utilities Code §38.103) requires every electric utility, municipally owned utility and electric cooperative that distributes power to the public to submit a Distribution Pole Management Plan to the Public Utility Commission of Texas. The statute sets an initial deadline of January 1, 2027, and the PUCT may set different filing dates for each type of utility.

These requirements make documented processes, clearly assigned responsibilities, inspection records, training and reliable data essential for all three types of Texas electric utilities.

A program that runs on email, spreadsheets and repeated field visits will struggle to meet these obligations, and will struggle even more to prove that it did.

Why More Software Alone Won’t Fix It

When these problems build up, the usual fix is to buy another tool. Each tool solves one piece, but tools stacked on top of each other create new gaps: more logins, more places to enter data, more exports and imports. Some also tie the utility to one vendor’s way of working for years.

We take a different approach. We don’t tie any client to a single software or platform. We start with the systems you already have and work with your team to connect them.

Our integration solutions link your field data collection, mapping, notification, work management and financial systems. Information captured once, whether in the field or in an application, moves directly to every system that needs it. Pole data collected in the field updates your maps. An approved application starts the notice to the attacher. Attachment counts carry through to billing. Fewer handoffs mean less re-entry, fewer errors and no lost records.

Where a gap remains, we fill it with widely available tools your staff can maintain, never a proprietary system that locks you in. The goal is simple: enter data once, keep one reliable record and let your team spend its time on the work, not the paperwork. The technology should serve your program, not the other way around.

Our Approach: Assess, Identify, Implement, Sustain

  1. Assess. We start by auditing your current program: your systems, data flows, attachment agreements, standards, fee schedules, staffing and workload. We meet with each group involved, including engineering, mapping, operations, billing, contracts and field crews, because the biggest problems usually sit where one group hands work to another.
  2. Identify. We map where the program slows down: where data is entered twice, where applications stall, where fielding is repeated, where documentation is thin and where revenue is lost. Then we rank these problems by cost, risk and effort to fix.
  3. Implement. We put cost-effective, scalable solutions in place across every part of the program:
    • Engineering: attachment standards, construction specifications, application review, pole loading analysis and make-ready design
    • Field work: field data collection, make-ready verification and post-construction inspections, planned so poles aren’t fielded twice
    • Mapping: pole and attachment data kept current in your GIS, so every group works from the same records
    • Administration: application workflows, attacher notifications, invoicing support, fee tracking and attachment inventory reconciliation
    • Compliance: agreement terms, NESC requirements, violation notices and regulatory reporting
    A municipal utility with a few hundred applications a year needs a different program than a large system handling thousands. We size the solution to your needs, your budget and your capacity to maintain it.
  4. Sustain. We don’t hand over a report and leave. We can manage the program alongside your team as one point of contact for your divisions, attaching entities and their contractors. We track performance and adjust as application volume, regulations and your organization change.

What This Looks Like in Practice

A West Texas municipal utility has worked with us since 2019. We wrote its wireline attachment specifications and standards, performed structural loading analysis under its own loading criteria, and built its application review and license agreement compliance workflow. When application volume grew, we hired and trained a local field data collection team to the utility’s requirements.

Since then, we have managed nearly 500 pole attachment applications covering approximately 9,800 poles across multiple attaching entities. Every application follows the same review standards, coordination with attachers runs through one point of contact, and agreement compliance is tracked in one place. The utility now has one team that knows its standards, its systems and its people.

How Aeparmia Helps Utilities Manage Pole Attachment Programs

Most utilities manage attachments through several consultants, contractors and internal groups. We provide one accountable team for the full program:

  • Pole attachment standards, license agreements, construction specifications and standard details
  • Program plans, standard operating procedures, application workflows, timelines and roles
  • Application review, pole loading analysis and make-ready design
  • Field data collection and post-construction inspections, planned so poles aren’t fielded twice
  • Make-ready documentation you can defend in an audit or dispute
  • Invoicing support, fee tracking and attachment inventory reconciliation
  • Training for utility staff, attaching entities and their contractors
  • Compliance management for agreement terms, NESC requirements, safety programs and regulatory reporting

Drawing on our experience supporting municipally owned utilities and public networks across Texas, we provide the engineering, field services and program management needed to build attachment programs that are efficient, compliant and sized to your organization.

The Bottom Line

Attachment demand is rising. Deadlines are fixed. Records have to hold up. Pole attachment programs aren’t one-time projects: agreements renew, technology changes, regulations tighten and application volume rises and falls. Utilities need a partner who understands both the engineering and the administration, who won’t lock them into a single platform, and who stays for the long term.

That’s our role. We take on the compliance burden and the inefficiencies, and we work with you to build the program that fits your organization.

Is your attachment program losing time and money? Contact us to schedule a pole attachment program assessment.

Contact Aeparmia Engineering | Austin · San Antonio · Lubbock

About the Author

Mia Diya-Bernhard, P.E., PMP is the President and CEO of Aeparmia Engineering, PLLC (TBPELS Firm No. 19271), a Texas-based civil engineering firm specializing in utilities infrastructure. Aeparmia serves electric utilities, electric cooperatives, and municipally owned utilities across Texas from offices in Austin, San Antonio, and Lubbock.

Sources

  • 47 U.S.C. §224, Pole attachments (uscode.house.gov)
  • 47 CFR §1.1411, Timeline for access to utility poles (ecfr.gov)
  • FCC, Fifth Report and Order, FCC 25-38, WC Docket No. 17-84 (July 2025); Small Entity Compliance Guide, DA 26-378 (April 16, 2026) (docs.fcc.gov)
  • FCC, Notice of OMB approval and effective date for amended pole attachment rules (Federal Register, May 7, 2026) (federalregister.gov)
  • Texas Utilities Code §54.204, Discrimination by Municipality Prohibited (statutes.capitol.texas.gov)
  • Texas Local Government Code Chapter 284, including §284.201, Municipally Owned Utility Poles (statutes.capitol.texas.gov)
  • Texas Utilities Code Chapter 253, Broadband Attachments to Electric Cooperative’s Distribution Poles (statutes.capitol.texas.gov)
  • Texas HB 144 (89th Legislature), Utilities Code §38.103, Distribution Pole Plan (capitol.texas.gov)
  • Aeparmia Insights, “Texas Changed the Rules on Utility Pole Inspections. Here’s What Every Power Utility Needs to Know.” (June 23, 2026) (aeparmia.com)

© 2026 Aeparmia Engineering, PLLC. All rights reserved. This article is for informational purposes only and does not constitute legal advice. Consult qualified legal counsel for compliance guidance specific to your utility.